Kammerer Road

The 6.5-mile Kammerer Road corridor between Interstate 5 and State Route 99 in Elk Grove is being implemented in partnership with the City of Elk Grove and County of Sacramento.

Status:

  • Environmental review complete.

  • Initial construction of 3-mile segment between Bruceville Road and SR 99 completed in 2023. City of Elk Grove is currently updating the General Plan for this segment.

  • Final engineering design between Interstate 5 and Bruceville Road will begin in 2024, with right of way acquisitions anticipated in 2025.

Grant Line Road

At 19 miles between State Route 99 and White Rock Road, the Grant Line Road corridor is the SouthEast Connector Expressway’s longest and is being implemented in partnership with the City of Elk Grove, County of Sacramento, and City of Rancho Cordova.

Status:

  • Grant Line Road interchange at SR 99 and nearby Union Pacific Railroad grade separation projects are complete.

  • Environmental review is complete and right of way acquisition is underway for improvements to the southern end of Bradshaw Road near Grant Line Road.

  • Development of a precise roadway plan including near-term intersection improvements is underway for the alignment between Bond Road and Calvine Road.

  • Environmental review on alignment between Calvine Road and SR 16 (Jackson Highway) is expected to be completed by 2030.

  • Environmental review is complete and right of way acquisition is underway for the alignment between SR 16 and White Rock Road.

White Rock Road

The 9-mile White Rock Road corridor between Grant Line Road and US Highway 50 is being implemented in partnership with the County of Sacramento, City of Folsom, and County of El Dorado.

Status:

  • Silva Valley Parkway interchange at Highway 50 is complete.

  • Environmental review of the alignment near the El Dorado Hills Town Center is underway.